Pm Link Blog How to Manage an Information Technology Project - Part 3/3

One mistake project managers make is calculating percent complete based on hours of effort spent versus total hours planned for the entire project. The fact that team members have expended two thousand hours on a planned ten thousand hour project does not mean that it is twenty percent complete. Rather,... Read more »